The following provides a description of the updates that have been made to the Aspen at Melford:

Completed this past month:

  • Lap siding completed at Building A1
  • Cabinets, countertops, and light fixtures began to be installed on lower levels of Building A1
  • Masonry veneer completed at Building A2
  • Insulation and drywall were completed at Building A2
  • Paint, tile, and door installation began at Building A2
  • Insulation and drywall began at Building B
  • Masonry Veneer and lap siding progressed at Building B
  • Wood framing completed at Buildings C & D
  • MEP rough-ins began at Building C
  • Site work began in the south courtyard, plaza, and garage entrance areas
  • Insulation and drywall progressed in the amenity areas

Upcoming this month:

  • Closet shelving, bath accessories, and window treatments will begin to be installed in Building A1
  • Doors, tile, cabinets, and countertops will be installed in Building A2
  • Lap siding will complete at Building A2
  • Insulation and drywall will progress at Building B
  • Masonry veneer and lap siding will be completed at Building B
  • MEP rough-ins will progress at Building C
  • Masonry veneer and lap siding will begin at Building C
  • Roofing and windows will complete at Building D
  • Site work will progress in the south courtyard, plaza, and garage entrance areas
  • Insulation and drywall will progress in the amenity areas